Back to Projects



Completed
LV-MV Switchgear Maintenance
Electrical MaintenanceLocation
Omoku Power Plant
Date
April 2025
Duration
7 days
Client
FIPL
Project Overview
This project covers the inspection and servicing of the Schneider SF2 MV circuit breakers 36KV, 2500A, inspection and maintenance of the switchgears which includes the circuit breakers, earth switches, isolating switches, CTs, PTs, busbars. The objective was to ensure the operational integrity and reliability of the switchgears by addressing the reported issues on the switchgears in alignment with OEM recommended standards and this was achieved by UNITRITECH within 7days of mobilization to site.